Floor Penetration E Kit Installation Instructions

../Installation Guides/Floor Penetration E Kit Installation Instructions

THIS PRODUCT HAS BEEN MANUFACTURED IN ACCORDANCE WITH AS/NZS 2918:2001. TO ENSURE SAFETY THIS PRODUCT MUST BE INSTALLED AS OUTLINED IN THESE INSTRUCTIONS. HEATER AND FLUE PIPE CLEARANCES FROM COMBUSTIBLE WALLS MUST BE IN ACCORDANCE WITH HEATER MANUFACTURER'S SPECIFICATIONS AND AS/NZS 2918:2001.

THIS PRODUCT SHALL ONLY BE USED ON APPLIANCES TESTED IN ACCORDANCE WITH AS/NZS 2918:2001.

  1. With heater located in its proposed position mark a point on the first floor/ceiling that is directly above the centre of heaters flue outlet. Check that the heater’s location allows the FLOOR PENETRATION UNIT to clear all structural floor timbers.

  2. Cut a 305mm square hole in the floor.

  3. Measure length from the surface of floor to ceiling below. If this measurement is less than 205mm the square CEILING SUPPORT UNIT will need to be trimmed accordingly.

  4. Fit the square CEILING SUPPORT UNIT into the ceiling/floor aperture, securing with screws or nails. The flange should be flush with the underside of the ceiling.

  5. Fit the MESH FLOOR PLATE into the CEILING SUPPORT UNIT and secure using the screws and spacers provided.

  6. The FLOOR PENETRATION E KIT is now ready for installing the OUTER/INNER CASING COMBINATION, FLUE PIPE and INSULATED CEILING PLATE


    The instructions for the FLOOR PENETRATION E KIT must be followed. This unit is designed for use with 250/200 outer/inner casing combination only.

    The Outer/Inner Combination must be continuous from the Floor Penetration Unit through ceiling and roof structures and ventilate at the casing cover.

    This unit is not designed for use with mesh screens.